Skip to main content
RECLAIM OUR INFRASTRUCTURE

Expose the Tunnel Deal

Declassify and publish all secret toll road contracts and traffic volume guarantees in full.

The contracts governing how much you pay to use Victorian toll roads are classified. You cannot read them. The liabilities the state accepted on your behalf are commercially confidential.

West Gate Tunnel's agreement with Transurban extended CityLink to 2045. The toll escalation formulas, the traffic volume guarantees, the state liability clauses — all of it is locked behind commercial-in-confidence rules. You're paying for these roads. You have no way to know what was agreed. Democratic accountability on infrastructure contracts requires public access to those contracts.

2045

Year the CityLink toll monopoly finally expires — locked in a secret contract you can't read

Department of Transport infrastructure disclosures

📊 Check Your Local Transport Score

How does your electorate stack up? Use our Victoria-wide transport scoring tool to check public transport frequency, coverage, and connectivity in your area.

Go to Transport Score Tool
What it costs

$0

Paid for by: Scrutiny and disclosure only — the Cross Yarra Partnership agreement runs to around 2050 and early modification would likely trigger compensation exceeding any gain, so this is a PAEC transparency push on availability payments, not a claw-back, alongside directing land-value uplift near the five new stations into the VWHF now.

What it does

  • End secret toll agreements

    Citizens gain complete access to the contracts governing public toll roads.

  • Expose taxpayer liabilities

    Secret state traffic volume guarantees and liability clauses are made public.

  • Enable contract renegotiation

    Public visibility of contract terms empowers transparent campaigns for fairer arrangements.

Secret contracts mean secret prices and secret liabilities. Publish them.

Further Detail

Design Rationale

The Metro Tunnel was announced in 2016 at roughly $11 billion and had cost at least $13.48 billion by September 2024, with some reporting citing $15.5 billion for the overall project scope. The project was structured as a fixed-price PPP with the Cross Yarra Partnership, on the basis that the private sector would carry construction and schedule risk. It did not work out that way: in December 2020 the state signed amending deeds under which it agreed to contribute up to an extra $1.37 billion toward construction costs, conditional on CYP hitting delivery milestones, and in 2024 further additional payments of up to $888 million were reported in connection with the opening timeline. The 25-year availability payment clock to CYP started in 2026, meaning the full cost of the deal will accumulate over a generation with no single point at which a reconciled total has been tabled.

System Interaction

The CYP Project Agreement is a Partnerships Victoria contract governed by DTF's 2016 Requirements. The 25-year operational concession gives CYP exclusive rights to manage commercial and retail opportunities across all five stations, up to 30 retail shops, station advertising, vending, and brand activations, running to roughly 2050. Unilaterally redirecting that retail to VWHF would trigger "no worse off" compensation clauses under the Project Agreement, requiring the state to pay CYP the net present value of 25 years of retail rent and advertising profit, which would likely exceed whatever VWHF could earn from the same space. The policy therefore targets the surrounding land, not the station footprint: Windfall Gains Tax and Infrastructure Contributions Plan levies on development sites around each of the five stations can flow into VWHF without touching CYP's contractual retail rights at all.

Economic & Institutional Logic

The original 2016 business case justified the PPP over conventional public procurement on a projected value-for-money saving of around $85 million over 10 years, against an $11 billion commitment: less than a tenth of one percent a year of the project's own headline cost. The state then paid out well over $2 billion in additional construction-phase contributions. CYP's 25-year availability payment stream, sized against the post-reset contract value, locks in regardless of how the construction phase went. The PAEC task is to get the post-reset contract value and the quarterly availability payment amounts onto the public record so that the total lifetime cost of the deal, construction plus 25 years of availability payments, can be compared against the public sector comparator the 2016 business case used.

Risk & Failure Modes

The government is unlikely to voluntarily produce a single reconciled figure covering construction costs, amending deeds, additional milestone payments, and 25-year availability payments, because that total is larger than any individual number that has been reported. The opposition's figure of up to $888 million in additional 2024 payments is contested and should be treated as unconfirmed pending PAEC. The risk for this policy is that PAEC produces partial disclosure, the government tables some numbers but withholds others under commercial-in-confidence claims, producing a reconciliation that is still incomplete. The Auditor-General's Phase 3 audit of the Metro Tunnel (Systems Integration, Testing and Commissioning) is the mechanism to test whether the commercial-in-confidence claims are legitimate or are used to obscure performance failures.

Evidence & Precedent

Portugal renegotiated 254 PPP contracts between 1995 and 2012, with private firms using each renegotiation to extract additional state payments, a pattern documented as systematic rent extraction through contract complexity. The Metro Tunnel's December 2020 reset follows the same template: the private consortium experienced cost overruns, mediated claims through an independent process, and extracted an additional $1.37 billion commitment from the state on top of the original contract price. The policy library's "Seven More Levers" section explicitly proposes a permanent PPP Renegotiation Unit within DTF to use the contractual step-in and default provisions on the state's terms rather than waiting for consortiums to initiate renegotiations on theirs. This is the mechanism Victoria has never deployed proactively.

Implementation Outline

This is a crossbench-leverage policy. A Fusion MP tables PAEC questions requiring DTF to publish a reconciled Metro Tunnel cost statement covering: (1) the original contract price, (2) all amending deeds and settlement payments including the December 2020 reset, (3) the post-reset availability payment schedule for the 25-year concession, and (4) the projected total of construction plus operational payments to CYP over the life of the concession. That reconciled total has never appeared in a single public document; putting it there is the one-seat deliverable. If DTF refuses, the Fusion MP requests a formal Phase 3 performance audit under the Audit Act 1994. The CYP retail rights cannot be clawed back without triggering compensation clauses that would cost more than they save; the one-seat mechanism on the surrounding land, directing WGT and ICP levies from the five station precincts into VWHF, does not require touching the Project Agreement and can be pursued independently via supply negotiations.

This policy won't pass itself.

Every vote we get is a vote against the system that's taking from you.

You Found the Secret!

True democracy rewards the curious. Here's something special for developers, gamers, and people who actually read the code...

THE ANNOTATED POLICY FILES

Every policy with the design rationale, evidence, and risk assessment behind it. This is the behind-the-scenes version our policy team uses internally.

View on GitHub

This entire site is open source. Fork it, learn from it, improve it.

View on GitHub

ZERO TRACKING

Check your browser dev tools. Major parties have 15+ tracking scripts. We have zero.

P.S. Share this with other curious people. Democracy needs more of them.